PERMISSION TO ERECT NEW LIFT



The Owner of a place where the lift is to be erected shall

  1. Ensure the lift erection company is manufacturing/uses the lift components as per BIS


  2. Furnish Duly filled in Form “A” in quadruplicate (Download form-A)


  3. Enclose quadruplicate copies of drawings duly signed by the Applicant and Authorized Person of Lift Company, showing Layout of the lift, Plan, Section elevation, Arrangement of doors, Lift well enclosure, Size and position of the machine relating to the lift well, Position of hoisting machine & Number of floors to be served and total travel height.


  4. Enclose quadruplicate copies of drawings duly signed by the Applicant and licenced Electrical Contractor, showing Wiring Scheme for the complete lift installation including earthing scheme showing size of earth leads, method of construction of earth electrode, laying of cables, etc.


  5. Copy of the building plan / civil plan approved from competent authority.


  6. Khata certificate from respective competent authority.


  7. Revenue Tax paid receipt of the building where lift is to be installed.


  8. Enclose original receipt or challon for Rs. 500/- (The amount shall be remitted at any Govt. Treasury or at Bank under head of account “0043” or at office cash counter.)


  9. Forward the above in complete to the respective Deputy Chief Electrical Inspector. (To know the Office location Click Here)

Permission to erect the lift will be granted by the respective Deputy Chief Electrical Inspector, if the application and enclosures are in order.

The erection Permission granted is valid for one year from the date of grant. The erection Permission granted can be extended further on receipt of application along with original challon/receipt for Rs. 500/-


The erection of the lift shall be carried out strictly according to the sanctioned drawings as well as per the provisions of Lifts Act and Rules.